Redlands Passenger Rail Project Construction Activities

By Redlands Passenger Rail Project

07/01/2019 at 09:43 AM

As the San Bernardino County Transportation Authority (SBCTA) begins the Rednlands Passenger Rail Project, crews will stat potholing in 2 segments. 

When: July 1-3 and July 5.

Hours: Daytime 7:00 a.m. to 3:30 p.m.

Where: Segment 1: Starting at E street and working East; Segment 2: Starting at Tippecanoe and working East.

Work: Potholing (vacuum excavation to obtain visual confirmation of utilities and underground obstructions).

Closures: If needed, one-way traffic control with flaggers will be used. Expect delays and drive cautiously.

Please remember all construction is dynamic and the schedule is weather-permitting and subject to change.